Activity duration

From PEaM

Jump to:navigation, search
PMI Activity duration is the time in calendar units between the start and finish of a schedule activity.[1]
AACEI Activity duration is:[2]
  1. Length of time from start to finish of an activity, estimated or actual, in working or calendar time units.
  2. Best estimate of continuous time (hours, days, weeks, and months) needed to complete the work involved in an activity. This takes into consideration the nature of the work, and the resources needed to complete the task. Baseline activity duration development can become very complex when productivity impacts and nonstandard production rates must be utilized to meet the constraints of the project.

See also

References

  1. Project Management Institute (2008). A Guide to The Project Management Body of Knowledge, 4th, Project Management Institute.
  2. Association for the Advancement of Cost Engineering International [AACEI] (2007). Cost Engineering Terminology, 10S-90, Association for the Advancement of Cost Engineering International.
PMBOK-4th.gif
This article contains text from the Project Management Institute PM Body of Knowledge which is copyright all rights reserved by Project Management Institute, Inc. (PMI). Project Management Body of Knowledge is a registered trademark of PMI
Aace2003logo.jpg
This article contains text from the Association for the Advancement of Cost Engineering website which is copyright all rights reserved by Association for the Advancement of Cost Engineering International (AACEI).
Navigation
Toolbox
Print/export