Activity splitting

From PEaM

Jump to:navigation, search
AACEI Activity splitting is the process of dividing (i.e., splitting) an activity of stated scope, description and schedule into two or more activities which are rescoped and rescheduled. The sum of the split activities is normally the total of the original. [1]

See also

References

  1. Association for the Advancement of Cost Engineering International [AACEI] (2007). Cost Engineering Terminology, 10S-90, Association for the Advancement of Cost Engineering International.
Aace2003logo.jpg
This article contains text from the Association for the Advancement of Cost Engineering website which is copyright all rights reserved by Association for the Advancement of Cost Engineering International (AACEI).