Actual finish date

From PEaM

Jump to:navigation, search
AACEI Actual finish date is the date when work on an activity is substantially complete. Activity substantial completion is when only minor or remedial work remains and successor activities may proceed without hindrance from the predecessor’s remaining work. It is not necessarily the last day work will be performed on that activity. The remaining duration of this activity is zero.[1]

References

  1. Association for the Advancement of Cost Engineering International [AACEI] (2007). Cost Engineering Terminology, 10S-90, Association for the Advancement of Cost Engineering International.
Aace2003logo.jpg
This article contains text from the Association for the Advancement of Cost Engineering website which is copyright all rights reserved by Association for the Advancement of Cost Engineering International (AACEI).
Navigation
Toolbox
Print/export