Actual finish date
From PEaM
| AACEI | Actual finish date is the date when work on an activity is substantially complete. Activity substantial completion is when only minor or remedial work remains and successor activities may proceed without hindrance from the predecessor’s remaining work. It is not necessarily the last day work will be performed on that activity. The remaining duration of this activity is zero.[1] |
|---|
References
- ↑ Association for the Advancement of Cost Engineering International [AACEI] (2007). Cost Engineering Terminology, 10S-90, Association for the Advancement of Cost Engineering International.