Backward pass
From PEaM
| PMI | A backward pass is the calculation of late finish dates and late start dates for the uncompleted portions of all schedule activities. Determined by working backwards through the schedule network logic from the project's end date.[1] |
|---|
| AACEI | A backward pass is a network schedule calculation that determines the latest each activity in the network may start (LS) and finish (LF) and still maintain the minimum overall duration of the project as calculated by the forward pass. It counts backward toward the beginning of the schedule to determine the last possible start and finish dates for each activity that will not delay project completion.[2] |
|---|
See also
- Backward pass
- Forward pass
- Schedule network analysis
References
- ↑ Project Management Institute (2008). A Guide to The Project Management Body of Knowledge, 4th, Project Management Institute.
- ↑ Association for the Advancement of Cost Engineering International [AACEI] (2007). Cost Engineering Terminology, 10S-90, Association for the Advancement of Cost Engineering International.
| This article contains text from the Project Management Institute PM Body of Knowledge which is copyright all rights reserved by Project Management Institute, Inc. (PMI). Project Management Body of Knowledge is a registered trademark of PMI |
| This article contains text from the Association for the Advancement of Cost Engineering website which is copyright all rights reserved by Association for the Advancement of Cost Engineering International (AACEI). |