Bottom-up estimating
From PEaM
Bottom-up estimating [PMI Technique] is a method of estimating a component of work. The work is decomposed into more detail. An estimate is prepared of what is needed to meet the requirements of each of the lower, more detailed pieces of work, and these estimates are then aggregated into a total quantity for the component of work. The accuracy of bottom-up estimating is driven by the size and complexity of the work identified at the lower levels.
References
| This article contains text from the Project Management Institute PM Body of Knowledge which is copyright all rights reserved by Project Management Institute, Inc. (PMI). Project Management Body of Knowledge is a registered trademark of PMI |